Composite Material, Rigid Board, R-Seal

CS Rigid Roof-Wall Gable Height Change

NOTES: * Field cut bottom of wall panels to match roof slope. Provide air gap of 1/4" min. at bottom of panel to avoid corrosion. ** Insulation is representative. Erector shall refer to insulation manufacturer’s installation information for further details/direction. The erector is responsible for providing the final solution for installation, air tightness, and performance of the liner insulation system.

BL

** ___" RIGID CONTINUOUS INSULATION (NOT BY CHIEF)

* WALL PANEL

HEIGHT CHANGE ANGLE (PL-x) #12-14 X ____"

DOUBLE BEAD TAPE MASTIC CS ROOF PANEL #12-14 X _____" (12" C.C.) HEIGHT CHANGE TRIM (RHT) INSIDE CLOSURE

(6" C.C. for CS PANEL) (12" C.C. for AP PANEL)

* 1 4 "

**___" RIGID CONTINUOUS INSULATION (NOT BY CHIEF)

#12-14 X 1" PANCAKE HEAD (2 EACH PURLIN)