MVF / MVP - Erection Manual

MVF/MVP M echanically S eamed V ertical Leg F lat M echanically S eamed V ertical Leg P encil-rib

®

GENERAL INFORMATION

PANEL STORAGE & HANDLING

Store bundled panels off of the ground sufficiently enough to allow air circulation beneath the bundle and to prevent rising water from entering the bundle. Elevate one end of the bundle to allow for water run-off. Prevent rain from entering bundle by covering with a tarpaulin, making provision for air circulation between the draped edges of the tarpaulin and the ground. PROLONGED STORAGE OF PANELS IN A BUNDLE IS NOT RECOMMENDED . If conditions do not permit immediate installation, extra care should be taken to protect panels from white rust or water marks.

Air Flow

Air Flow

15’-20’

15’-20’

8’-10’

Standing on one side of the panel, lift it by the seam. The longer the panel, the more personnel needed to transport. DO NOT BUCKLE THE PANEL. DO NOT PICK PANELS UP BY THE ENDS.

NOTE Protective gloves and safety glasses should always be used while handling panels. OSHA safety regulations must be followed at all times.

WRONG WAY

Version 2.0

SUBJECT TO CHANGE WITHOUT NOTICE

MVF/MVP-13