MVF / MVP - Erection Manual
MVF/MVP M echanically S eamed V ertical Leg F lat M echanically S eamed V ertical Leg P encil-rib
®
DETAILS
GABLE RIDGE TRIM
1. Install gable trim to 4” from center line of building each way.
4"
4"
GABLE TRIM
CENTER LINE OF BUILDING
GABLE TRIM
ROOF PANEL
OUTSIDE CLOSURE
DOUBLE BEAD TAPE MASTIC
GABLE TRIM
DOUBLE BEAD TAPE MASTIC (Marry the mastic from the gable trim and outside/ridge closure) 2. Place Double Bead Tape Mastic as shown.
Version 2.0
SUBJECT TO CHANGE WITHOUT NOTICE
MVF/MVP-47
Made with FlippingBook - Online catalogs