Special Features
Eave Strut to Col w 6-8 flange and MVF-MVP Roof Trans Exp w Thermal Spacer
** MAINTAIN 2 1/2" BETWEEN FIXED AND SLIDING EAVE STRUT DURING BUILDING ERECTION SPECIAL PUNCH 9/16" HOLES AT 1 3/8" DIM A AND 4 1/4" GAGE IN BOTH EAVE STRUTS
* FINGER TIGHTEN 1ST 1/2" DIA. NUT TO HARD WASHER, WRENCH TIGHTEN SECOND NUT TO FIRST NUT TO CREATE A SLIDING CONNECTION
1
CL
4 1 2 " 1 1 4 "
XBC-96
REF PT
SLIDING EAVE STRUT
1 1 4 "
1 3 8 " 4 1 4 "
* (2) 1/2" X 1 3/4" BOLTS w/ (2) NUTS AND (1) 1/2" HARD WASHER AT EACH SLOT (BOLT MUST BE CENTERED IN SLOT) FRAME COLUMN EAVE HEIGHT
3 1 4 "
**2 1 2 "
(4) 1/2" X 1 1/4" BOLTS FIXED EAVE STRUT (4) 5/8" X 1 1/2" BOLTS w/ 5/8" HARD WASHERS AT C-SECTION SIDE