MVF / MVP - Erection Manual
MVF/MVP M echanically S eamed V ertical Leg F lat M echanically S eamed V ertical Leg P encil-rib
®
GENERAL INFORMATION
BEFORE YOU GET STARTED
Chief’s MVF/MVP roof is detailed to flow in a certain direction. Panel flow direction is defined in the erection drawings Roof Panel Plan.
FLOW
FLOW
4
1 2 3 4 5 6
1
RIDGE
!! Important !! The erection drawings will show the starting position and the flow of the panels.
5
1 2 3 4 5 6
2
FLOW
6
3
Example of Panel Sequence per slope
MVF/MVP panels MUST be erected from eave to ridge.
RIDGE
3
6
2
5
The drawings will show the location of the panels. Each panel mark suffix contains the length of the panel (in inches). Each panel prefix (i.e. 3RV, 6RV) determines the end conditions that are built into the ends of the panels. It is VERY important that the panel layout of erection be followed.
1
4
FLOW
Example of Panel Sequence per slope w/ panel splices
4RV... 8RV... 6RV... 5RV... 7RV... 3RV...
3RV... 7RV... 5RV... 6RV... 8RV... 4RV...
Panel Prefix
Lead Condition
Tail Condition
1RV 2RV 3RV 4RV 5RV 6RV 7RV 8RV 9RV
NONE RIDGE NONE NOTCH SWAGE RIDGE SWAGE NOTCH
RIDGE NONE NOTCH NONE RIDGE SWAGE NOTCH SWAGE
RIDGE
NONE NONE
NONE
10RV 11RV
SWAGE
SWAGE
NONE
Also refer to eave and gable details located in the Detail section of the erection drawings.
Example of Panel Marks
Version 2.0
SUBJECT TO CHANGE WITHOUT NOTICE
MVF/MVP-17