MVF / MVP - Erection Manual

MVF/MVP M echanically S eamed V ertical Leg F lat M echanically S eamed V ertical Leg P encil-rib

®

ERECTION SEQUENCE

STEP 2 cont'd

INSULATION Apply Double Bead Tape Mastic to the trim cap.

DOUBLE BEAD TAPE MASTIC

DOUBLE FACED TAPE (BY INSULATION SUPPLIER)

TRIM CAP

EAVE STRUT

WALL PANEL

Roll out insulation from eave to peak laying the side of the insulation on top of rake angle, butted up to the clips. The first roll should be 6' wide. If the remaining insulation widths are 4’, this will keep insulation sidelaps 8” from roof panel sidelaps. Allow approximately 4" of insulation to hang past the double faced tape (down slope) before sticking the insulation to the double faced tape. Cut and remove the fiberglass approximately 4" and fold the vapor retarder back over the insulation (upslope). The vapor retarder should marry into the endwall insulation’s vapor retarder.

DOUBLE BEAD TAPE MASTIC

DOUBLE FACED TAPE (BY INSULATION SUPPLIER)

CUT FIBERGLASS FROM VAPOR RETARDER AND FOLD VAPOR RETARDER OVER

SUBJECT TO CHANGE WITHOUT NOTICE CAUTION The fiberglass insulation must not interfere with the Double Bead Tape Mastic which provides a positive seal at the eave.

TRIM CAP

MVF/MVP-22

Version 2.0