MVF/MVP M echanically S eamed V ertical Leg F lat M echanically S eamed V ertical Leg P encil-rib
®
ERECTION SEQUENCE
STEP 12
BL
1"
LAST PANEL RUN Before you lay the last panel, install clips 1” from Building Line with (2)#12-14 x 1-1/4" fasteners, wall color. Clips are to be located in close proximity to purlins as discussed in Step 1.
Insulation is not shown for clarity.
BL
A-20-B ANGLE W/ (2)#12-14 X 1 1/4" FASTENERS
Install A-20-B angle to the clips with (2)#12 14 x 1-1/4” fasteners at each clip, wall color.
BL
Locate the Double Bead Tape Mastic edge at 1 3/4” from Building Line. Measure remaining coverage to Building Line. Using snips, electric nibblers, or electric shears, field cut the last panel to width.
X X - 1 3/4"
1 3/4"
DOUBLE BEAD TAPE MASTIC
BL
X - 1 3/4"
Roll last panel into place. Install temporary fasteners. This will be replaced with gable trim screws later on. Insure temporary fasteners are installed in a location that will be covered when the gable trim is installed.
TEMPORARY FASTENER
Version 2.0
SUBJECT TO CHANGE WITHOUT NOTICE
MVF/MVP-35