MVF / MVP - Erection Manual
MVF/MVP M echanically S eamed V ertical Leg F lat M echanically S eamed V ertical Leg P encil-rib
®
ERECTION SEQUENCE
STEP 4
1
SEE ERECTION DRAWINGS
ROOF PANEL
FIRST PANEL Refer to the erection drawings for the roof panel overhang dimension. Maintain this overhang amount as you progress down the sidewall. The eave line of roof panels must be installed straight and true.
DOUBLE BEAD TAPE MASTIC
TRIM CAP
While maintaining the eave overhang amount, roll the first panel into place. Make sure that all clips are engaged by the panel. If required, lift the male edge of the panel back up to get all of the clips engaged.
Check the eave overhang amount at this time. ANY ADJUSTMENTS MUST BE MADE AT THIS TIME.
MVF/MVP-24