MVF MVP Roof Panel
MVF-MVP Gable Tail End Height Change w Cut Roof Panel
* Field cut bottom of wall panels to match roof slope. Provide air gap of 1/4" min. at bottom of panel to avoid corrosion.
ROOF PANEL CUT BACK DIM. CLIP LOCATION FROM B
BL
L
**NOTE: This fastener must not hit the purlin.
2 1 4 "
HEIGHT CHANGE TRIM BOTTOM (GHVB) HEIGHT CHANGE TRIM TOP (GHVT)
1 1 2 "
*WALL PANEL INSIDE CLOSURE #12-14 X 1 1/4"
DOUBLE BEAD TAPE MASTIC 1/4-14 X 1 1/4" WT (6" C.C.)** TAPE MASTIC (2) #12-14 X 1 1/4" (EACH CLIP) WALL COLOR
(6" C.C. for CS PANEL) (12" C.C. for AP PANEL)
MVF/MVP ROOF PANEL RAKE ANGLE (A-20-B)
***
1
4 "
PRE-GLUED THERMAL SPACER (NOT BY CHIEF)
DOUBLE BEAD TAPE MASTIC
RAKE ANGLE (A-20-L)
PANEL CLIP w/FASTENERS (REFER TO ROOF PANEL PLAN)
PANEL CLIP w/FASTENERS (REFER TO ROOF PANEL PLAN)
PURLIN
***DRAFTING NOTE: Thermal spacer to be used with no insulation.
#12-14 X 1 1/4" (2 EACH PURLIN) (WALL COLOR)