Special Steel Framing
OSHA PLT TO WEB OF WF COLUMN
MEZZANINE FLOOR DECKING
"NEAR OSHA COLUMN" JOIST REQUIRES BOLTED ENDS W/WASHERS. SEE PLAN VIEW FOR LOCATIONS AND BOLT REQUIREMENTS
1/4" 1/4"
6" 6"
3"
MEZZANINE ELEVATION
HOLD
NEAR OHSA COLUMN JOIST
FLOOR BEAM
STABILIZER PLATE (PL-x) PLATE MAY BE REMOVED AFTER ERECTION IS COMPLETED. JOIST CHORDS TO SET ASTRIDE STABILIZER CLIP NO WELDING IS PERMITTED
NEAR OSHA COLUMN JOIST FIELD WELDED STABILIZER PLATE REQUIRED. CLIP TO BE INSTALLED PRIOR TO ERECTING JOIST. Ø13/16" HOLE PROVIDED FOR ERECTION GUYING OR PLUMBING CABLES.